Dau Tieng 5 Solar Power Plant is located in Suoi Da Commune, Minh Chau District, Tay Ninh Province. The plant is expected to generate an output of nearly 800 million kWh/year. The commercial operation date (COD) of the project is scheduled for between late 2023 and early 2024. After completion, the plant will increase the total capacity of Dau Tieng solar power projects cluster to 950MW out of the approved total capacity of 2,000MW.

Introduction
General information
-
Developer
:
DT5.1 Energy Joint Stock Company
-
Location
:
Suoi Da Commune, Duong Minh Chau Dist., Tay Ninh province
-
Total area
:
645ha
Total capacity
450MW
Total investment
> 7,000
billion dong
Start Date
QII/2022